Which is a type of issue?
A) A lesson
B) A request for change
C) An Exception Report
D) A risk with an estimated high impact
Correct Answer:
Verified
Q4: Which task is performed by the Change
Q5: Identify the missing word in the following
Q6: During the Managing a Stage Boundary process
Q7: Where should an off-specification be recorded?
A) Risk
Q8: Which should be funded by a change
Q10: Which is a benefit of using PRINCE2?
A)
Q11: Identify the missing word(s) in the following
Q12: Which statement is FALSE?
A) A project outcome
Q14: Which is a purpose of the Risk
Q18: Which is a responsibility of the managing