Identify the missing words in the following sentence, The six aspects of project performance to be managed are [?] costs, timescales and scope,
A) benefits, progress, risk,
B) benefits, quality, risk,
C) change, quality, progress,
D) benefits, customers, quality,
Correct Answer: