Which describes the 'Implement' step within the recommended risk management procedure?
A) Project Support will allocate the risk budget to fund the selected risk responses
B) The risk owner will decide the best response to control the risk
C) The risk owner and the risk actionee will carry out activities to control and deal with the risk
D) The Project Manager will formulate the Risk Management Strategy
Correct Answer:
Verified
Q28: Which of the following statements about the
Q31: Identify the missing words in the following
Q35: Which provides a single source of reference
Q36: Which describes the 'Identify Risks' step within
Q40: Which is NOT a purpose of the
Q46: When are tolerances for a Work Package
Q47: Which regular report provides the Project Board
Q53: Which is an objective of the quality
Q54: What process is used by the Project
Q58: Which product is NOT created in the
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents