Which is a purpose of the Risk theme?
A) Establish a method for the implementation of continuous improvement during the project
B) Identify, assess and control problems that have occurred
C) Provide the Project Board with a time-driven control to capture all project risks
D) Establish a cost-effective procedure to identify, assess and control risks
Correct Answer:
Verified
Q74: Identify the missing word in the following
Q76: Which is a responsibility of a Team
Q77: What do acceptance criteria identify?
A) The approach
Q78: Which is a benefit of using PRINCE2?
A)
Q80: Identify the missing words in the following
Q81: Identify the missing words in the following
Q82: What product should be used to confirm
Q83: Which is an objective of the Controlling
Q84: Which is a true statement about management
Q86: Which PRINCE2 principle helps to address a
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents