A Stakeholder Is Unaware of a Project's Status

Question 10

Multiple Choice

A stakeholder is unaware of a project's status. Which of the following documents should the project manager consult to ensure all stakeholders are notified of project changes? (Choose two.)


A) Status report
B) Organizational chart
C) RACI matrix
D) Meeting minutes
E) Communication plan