A project team is overseeing the installation of a new reptile habitat at the local zoo. During execution, zoo personnel decides to house a different type of reptile that will require a different temperature range than the capacity of the installed system. The modification has been approved. Which of the following constraints are MOST likely to be affected? (Choose two.)
A) Quality because the existing system is now outside the threshold.
B) Requirements because this is a change to initial scope.
C) Cost because replacing the system incurs additional expense.
D) Schedule because this was an unscheduled task and will impact the timeline.
E) Stakeholders because they will need to understand the modification and provide buy-in.
Correct Answer:
Verified
Q21: During the execution phase of a project,
Q22: Which of the following is a definition
Q23: During a project assessment, a project manager
Q24: A customer will have ongoing changes to
Q25: Two team members have concluded that documentation
Q27: Which of the following project documents should
Q28: Several team members report that meeting objectives
Q29: Which of the following individuals is MOST
Q30: Assuming an iterative approach, which of the
Q31: A project in the execution phase is
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents