Solved

A Project Team Is Overseeing the Installation of a New

Question 26

Multiple Choice

A project team is overseeing the installation of a new reptile habitat at the local zoo. During execution, zoo personnel decides to house a different type of reptile that will require a different temperature range than the capacity of the installed system. The modification has been approved. Which of the following constraints are MOST likely to be affected? (Choose two.)


A) Quality because the existing system is now outside the threshold.
B) Requirements because this is a change to initial scope.
C) Cost because replacing the system incurs additional expense.
D) Schedule because this was an unscheduled task and will impact the timeline.
E) Stakeholders because they will need to understand the modification and provide buy-in.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents