A project manager is providing the lessons learned for a project that ran over budget and produced poor quality deliverables. Which of the following should the project manager include as part of the lessons learned?
A) Risk register
B) Post-mortem analysis
C) Issue log
D) Procurement report
Correct Answer:
Verified