The project manager is reviewing the earned value of work completed compared to the planned value and is representing it in a dollar figure. This type of analysis is an example of which of the following?
A) Cost performance index
B) Risk mitigation
C) Schedule variance
D) Cost variance
Correct Answer:
Verified