Solved

A Subcontractor Has Submitted Design Documentation on the Deliverable Due

Question 128

Multiple Choice

A subcontractor has submitted design documentation on the deliverable due date, but it will require rework. The activity is on the critical path of the project schedule. Which of the following should the project manager do NEXT?


A) Determine the expected duration of the rework and complete a charge request to modify the project baselines.
B) Notify the project sponsor to schedule and facilitate a team meeting to rework the design documentation.
C) Determine the expected duration of the rework with any associated quality control activities and add the duration to an updated version of the WBS.
D) Update the master project schedule, and distribute it all stakeholders in accordance with the project communications plan.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents