A subcontractor has submitted design documentation on the deliverable due date, but it will require rework. The activity is on the critical path of the project schedule. Which of the following should the project manager do NEXT?
A) Determine the expected duration of the rework and complete a charge request to modify the project baselines.
B) Notify the project sponsor to schedule and facilitate a team meeting to rework the design documentation.
C) Determine the expected duration of the rework with any associated quality control activities and add the duration to an updated version of the WBS.
D) Update the master project schedule, and distribute it all stakeholders in accordance with the project communications plan.
Correct Answer:
Verified
Q123: A project team is defining detailed risks.
Q124: A client has provided a list of
Q125: A project has passed a phase-gate, and
Q126: Which of the following are mutually binding
Q127: A project manager procures additional resources from
Q129: Which of the following statements are correct
Q130: During the testing phase, a team member
Q131: A project manager receives a call from
Q132: An active project has a CPI of
Q133: An organization has determined that all projects
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents