A task on the critical path will not be completed on time. The project manager is reviewing both the schedule and the risk register to create a corrective action plan. The project completion date and quality of the deliverable cannot change. Which of the following activities should the project manager perform NEXT?
A) Revise the project plan.
B) Update the issue log.
C) Request additional funding.
D) Issue a change request.
Correct Answer:
Verified
Q155: At a project kickoff meeting, several team
Q156: Which of the following information does the
Q157: A project encountered a problem and reached
Q158: Which of the following conflict resolution techniques
Q159: Before a team can start on a
Q161: A PM is reviewing bids from vendors
Q162: Due to a lack of adherence to
Q163: A project sponsor, project manager, and project
Q164: The Chief Executive Officer (CEO) has announced
Q165: The project manager needs to motivate the
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents