During an ad-hoc meeting, the PM notifies the sponsor that while the project is on schedule, material costs have increased and the project is over budget. To save the project, the PM request a material contract with a less expensive vendor. The sponsor approves the change, and project comes in within target tolerances. The company, however, receives numerous stakeholder complaints. Which of the following is the MOST likely cause of these complaints?
A) The quality of the deliverable decreased due to the rising material cost.
B) The PM did not follow the project communication plan.
C) Quality assurance actions were not adjusted for the vendor change.
D) The change was not documented and approved.
Correct Answer:
Verified
Q177: A project team is not delivering their
Q178: Communication on a project is flowing well.
Q179: A new contractor joining the project team
Q180: A primary work location is unsafe due
Q181: On an OBS chart, there is a
Q183: Which of the following is the primary
Q184: Project status meetings have poor attendance. A
Q185: Which of the following metrics demonstrates to
Q186: Expenditure tracking helps with cost:
A) reporting
B) scheduling
C)
Q187: Based on the table below:
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents