A Resource Is Assigned to Two Projects with Two Scheduled

Question 250

Multiple Choice

A resource is assigned to two projects with two scheduled tasks that complete at the same time. This is known as:


A) shared resource contention
B) intraproject resource contention
C) interproject resource contention
D) dedicated resource contention

Correct Answer:

verifed

Verified