A fire occurred in the production facility over the weekend, affecting the machinery being used to produce a deliverable. No injuries were reported. Which of the following is MOST appropriate for the project manager to do NEXT?
A) Refer to the contingency plan
B) Conduct an immediate emergency team meeting
C) Perform a SWOT analysis
D) Implement the risk response plan
Correct Answer:
Verified
Q258: A project schedule lists a resource as
Q259: A project has fallen behind schedule for
Q260: Which of the following describes KPIs?
A) Analyses
Q261: A new project manager is working in
Q262: Given the information in the table below,
Q264: A local company is part of a
Q265: A PM has notified the project team
Q266: Which of the following charts is a
Q267: The Chief Executive Officer (CEO) has changed
Q268: A project manager has developed the initial
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents