A New Project Manager Is Working in an Environment Where

Question 261

Multiple Choice

A new project manager is working in an environment where resources report to another supervisor. The project manager is having difficulty with a particular member and wants to escalate the issue. Which of the following documents should the project manager consult?


A) Issue log
B) RACI chart
C) Risk management plan
D) Organizational chart

Correct Answer: