Solved

A Key Stakeholder Asked Several Members of the Project Team

Question 288

Multiple Choice

A key stakeholder asked several members of the project team to make project changes without submitting them for approval. Because the stakeholder is related to the Chief Executive Officer (CEO) , the team members are reluctant to deny these requests. Which of the following should the project manager do FIRST to control this situation?


A) Have the team members deny all change requests from this stakeholder
B) Ask the project sponsor for more funding to anticipate the change requests from the key stakeholder
C) Contact the key stakeholder to encourage the submission of written change requests
D) Request additional resources from the project team to complete the change requests from the key stakeholder

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents