A key stakeholder asked several members of the project team to make project changes without submitting them for approval. Because the stakeholder is related to the Chief Executive Officer (CEO) , the team members are reluctant to deny these requests. Which of the following should the project manager do FIRST to control this situation?
A) Have the team members deny all change requests from this stakeholder
B) Ask the project sponsor for more funding to anticipate the change requests from the key stakeholder
C) Contact the key stakeholder to encourage the submission of written change requests
D) Request additional resources from the project team to complete the change requests from the key stakeholder
Correct Answer:
Verified
Q283: A new project has just commenced. Project
Q284: While preparing to plan a project, the
Q285: An organization wants assurance that the specialty
Q286: Which of the following job roles is
Q287: Which of the following resources outlines consequences
Q289: A project manager is scheduling activities and
Q290: Which of the following primary factors are
Q291: An active construction project must make immediate
Q292: In a Scrum retrospective, which of the
Q293: During a risk review session, the project
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents