A key stakeholder has communicated a significant project scope change to the project manager. Which of the following actions should the project manager take FIRST?
A) Submit a change request to the CCB.
B) Implement the change to the project.
C) Determine the impact of the requested change.
D) Update the schedule to accommodate the change.
Correct Answer:
Verified
Q340: Which of the following are the components
Q341: Which of the following are major characteristics
Q342: When developing a project schedule, which of
Q343: Which of the following is a component
Q344: A project manager is not going to
Q346: A project manager is assigned to a
Q347: Which of the following is the BEST
Q348: Which of the following includes setting governance
Q349: Language barriers will MOST likely influence a
Q350: Which of the following charts would indicate
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents