A number of requirements, conflicts, and reworks during a project delayed the schedule, increased the budget, and required replanning efforts. Which of the following is MOST likely the cause?
A) There were not enough resources assigned to the project execution team.
B) The PMO was not involved in project initiation and planning.
C) Proper team-building activities were not performed when starting the project.
D) A few major stakeholders were overlooked during project initiation and planning.
Correct Answer:
Verified
Q373: A developer is experiencing constant project scope
Q374: A hurricane occurs in an area where
Q375: Which of the following is the BEST
Q376: A sprint retrospective is being conducted. Which
Q377: The Chief Executive Officer (CEO) of a
Q379: An audit, project change, task initiation/completion, gate
Q380: Which of the following organizational structures uses
Q381: A project team is creating a new
Q382: Which of the following describes the difference
Q383: A project manager was reprimanded for failing
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents