Severe weather has impacted a construction project, delaying scheduled work for five days. Which of the following project changes is the project manager most likely to consider FIRST?
A) Requirements change
B) Funding change
C) Timeline change
D) Risk event
Correct Answer:
Verified
Q453: Based on the table below:
Q454: Which of the following features describe a
Q455: An employee is assigned to a project
Q456: A project manager is not required to
Q457: Which of the following make up a
Q459: The following tasks are required to complete
Q460: A project manager wants to ensure that
Q461: Which of the following events would MOST
Q462: A PM has a complex project that
Q463: A key stakeholder cannot identify within the
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents