Gas prices were included in the cost baseline for a transportation and hauling project. Although the estimates used to create the baseline were based on historical data, which of the following should the project manager consider as a root cause for potential issues with cost overruns?
A) Requirements
B) Lessons learned
C) Budget
D) Environment
Correct Answer:
Verified
Q440: Which of the following describes risk mitigation?
A)
Q441: A vendor advises the project manager that
Q442: A project team is identifying, rating the
Q443: Which of the following documents should the
Q444: Which of the following will identify the
Q446: A project manager is assigned to a
Q447: A minor change to the baseline schedule
Q448: A project manager is procuring new equipment
Q449: A key stakeholder asks the project manager
Q450: During the planning phase, the project manager
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents