The PMO is confused by an entry in the risk register and would like the project manager to provide clarification regarding strategy. Based on the following entry:
Which of the following should be modified to BEST eliminate confusion?
A) Change the status to issue and include it in the issue log
B) Change the strategy to mitigate
C) Change the name to identify the problem clearly
D) Change the owner to sponsor
Correct Answer:
Verified
Q475: During a CCB, a SME evaluated the
Q476: Which of the following represents the order
Q477: A project sponsor approaches the project manager
Q478: The internal project sponsor is frustrated by
Q479: A project needs two more months of
Q481: A project team is spread between two
Q482: During a project, a key stakeholder asks
Q483: In which of the following categories does
Q484: A new stakeholder has requested the status
Q485: One of the tasks on a project's
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents