You are the project manager for your organization. You have identified a risk event you're your organization could manage internally or externally. If you manage the event internally it will cost your project $578,000 and an additional $12,000 per month the solution is in use. A vendor can manage the risk event for you. The vendor will charge $550,000 and $14,500 per month that the solution is in use. How many months will you need to use the solution to pay for the internal solution in comparison to the vendor's solution?
A) Approximately 13 months
B) Approximately 11 months
C) Approximately 15 months
D) Approximately 8 months
Correct Answer:
Verified
Q13: The Project Risk Management knowledge area focuses
Q14: Which of the following individuals informs all
Q15: Certification and Accreditation (C&A or CnA) is
Q16: Which of the following administrative policy controls
Q17: You and your project team are just
Q19: You work as a project manager for
Q20: In which of the following testing methodologies
Q21: In which of the following Risk Management
Q22: Which of the following individuals is responsible
Q23: Which of the following is NOT a
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents