Question 37

Multiple Choice

Kelly is the project manager of the BHH project for her organization. She is completing the risk identification process for this portion of her project. Which one of the following is the only thing that the risk identification process will create for Kelly?


A) Project document updates
B) Risk register updates
C) Change requests
D) Risk register

Correct Answer:

verifed

Verified