Sammy is the project manager for her organization. She would like to rate each risk based on its probability and affect on time, cost, and scope. Harry, a project team member, has never done this before and thinks Sammy is wrong to attempt this approach. Harry says that an accumulative risk score should be created, not three separate risk scores. Who is correct in this scenario?
A) Sammy is correct, because organizations can create risk scores for each objective of the project.
B) Harry is correct, because the risk probability and impact considers all objectives of the project.
C) Harry is correct, the risk probability and impact matrix is the only approach to risk assessment.
D) Sammy is correct, because she is the project manager.
Correct Answer:
Verified
Q19: You work as a project manager for
Q20: In which of the following testing methodologies
Q21: In which of the following Risk Management
Q22: Which of the following individuals is responsible
Q23: Which of the following is NOT a
Q25: What does RTM stand for?
A) Resource Testing
Q26: Which of the following are the tasks
Q27: The Information System Security Officer (ISSO) and
Q28: Which of the following individuals is responsible
Q29: Which of the following professionals plays the
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents