You Are Preparing to Start the Qualitative Risk Analysis Process

Question 47

Multiple Choice

You are preparing to start the qualitative risk analysis process for your project. You will be relying on some organizational process assets to influence the process. Which one of the following is NOT a probable reason for relying on organizational process assets as an input for qualitative risk analysis?


A) Information on prior, similar projects
B) Review of vendor contracts to examine risks in past projects
C) Risk databases that may be available from industry sources
D) Studies of similar projects by risk specialists

Correct Answer: