Amy is the project manager for her company. In her current project the organization has a very low tolerance for risk events that will affect the project schedule. Management has asked Amy to consider the affect of all the risks on the project schedule. What approach can Amy take to create a bias against risks that will affect the schedule of the project?
A) She can have the project team pad their time estimates to alleviate delays in the project schedule.
B) She can create an overall project rating scheme to reflect the bias towards risks that affect the project schedule.
C) She can filter all risks based on their affect on schedule versus other project objectives.
D) She can shift risk-laden activities that affect the project schedule from the critical path as much as possible.
Correct Answer:
Verified
Q98: Harry is the project manager of the
Q99: Which of the following statements about Discretionary
Q100: What are the subordinate tasks of the
Q101: What component of the change management system
Q102: Which of the following statements best describes
Q104: Which of the following are the goals
Q105: Which of the following recovery plans includes
Q106: Which of the following is an entry
Q107: You work as a project manager for
Q108: The National Information Assurance Certification and Accreditation
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents