Jenny Is the Project Manager for the NBT Projects

Question 139

Multiple Choice

Jenny is the project manager for the NBT projects. She is working with the project team and several subject matter experts to perform the quantitative risk analysis process. During this process she and the project team uncover several risks events that were not previously identified. What should Jenny do with these risk events?


A) The events should be determined if they need to be accepted or responded to.
B) The events should be entered into qualitative risk analysis.
C) The events should continue on with quantitative risk analysis.
D) The events should be entered into the risk register.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents