Amy is the project manager for her company. In her current project the organization has a very low tolerance for risk events that will affect the project schedule. Management has asked Amy to consider the affect of all the risks on the project schedule. What approach can Amy take to create a bias against risks that will affect the schedule of the project?


A) She can have the project team pad their time estimates to alleviate delays in the project schedule.
B) She can shift risk-laden activities that affect the project schedule from the critical path as much as possible.
C) She can create an overall project rating scheme to reflect the bias towards risks that affect the project schedule.
D) She can filter all risks based on their affect on schedule versus other project objectives.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents