A project team member has just identified a new project risk. The risk event is determined to have significant impact but a low probability in the project. Should the risk event happen it'll cause the project to be delayed by three weeks, which will cause new risk in the project. What should the project manager do with the risk event?
A) Add the identified risk to a quality control management control chart.
B) Add the identified risk to the risk register.
C) Add the identified risk to the issues log.
D) Add the identified risk to the low-level risk watchlist.
Correct Answer:
Verified
Q178: The Phase 2 of DITSCAP C&A is
Q179: Which of the following is used to
Q180: Adrian is the project manager of the
Q181: You are the project manager for TTP
Q182: Which of the following approaches can be
Q184: Which of the following concepts represent the
Q185: Adrian is a project manager for a
Q186: The National Information Assurance Certification and Accreditation
Q187: Which of the following is a risk
Q188: Mary is the project manager of the
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents