A Project Team Member Has Just Identified a New Project

Question 183

Multiple Choice

A project team member has just identified a new project risk. The risk event is determined to have significant impact but a low probability in the project. Should the risk event happen it'll cause the project to be delayed by three weeks, which will cause new risk in the project. What should the project manager do with the risk event?


A) Add the identified risk to a quality control management control chart.
B) Add the identified risk to the risk register.
C) Add the identified risk to the issues log.
D) Add the identified risk to the low-level risk watchlist.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents