The phase 3 of the Risk Management Framework (RMF) process is known as mitigation planning. Which of the following processes take place in phase 3? Each correct answer represents a complete solution. Choose all that apply.
A) Identify threats, vulnerabilities, and controls that will be evaluated.
B) Document and implement a mitigation plan.
C) Agree on a strategy to mitigate risks.
D) Evaluate mitigation progress and plan next assessment.
Correct Answer:
Verified
Q196: You work as the project manager for
Q197: Which of the following individuals is responsible
Q198: Which of the following system security policies
Q199: Penetration testing (also called pen testing) is
Q200: Which of the following guidance documents is
Q202: Which of the following phases begins with
Q203: You work as the project manager for
Q204: Which of the following objectives are defined
Q205: The Chief Information Officer (CIO), or Information
Q206: Bill is the project manager of the
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents