Solved

You Work as a Project Manager for BlueWell Inc

Question 209

Multiple Choice

You work as a project manager for BlueWell Inc. Management has asked you to work with the key project stakeholder to analyze the risk events you have identified in the project. They would like you to analyze the project risks with a goal of improving the project's performance as a whole. What approach can you use to achieve the goal of improving the project's performance through risk analysis with your project stakeholders?


A) Involve subject matter experts in the risk analysis activities
B) Focus on the high-priority risks through qualitative risk analysis
C) Use qualitative risk analysis to quickly assess the probability and impact of risk events
D) Involve the stakeholders for risk identification only in the phases where the project directly affects them

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents