Tom is the project manager for his organization. In his project he has recently finished the risk response planning. He tells his manager that he will now need to update the cost and schedule baselines. Why would the risk response planning cause Tom the need to update the cost and schedule baselines?
A) New or omitted work as part of a risk response can cause changes to the cost and/or schedule baseline.
B) Risk responses protect the time and investment of the project.
C) Baselines should not be updated, but refined through versions.
D) Risk responses may take time and money to implement.
Correct Answer:
Verified
Q239: Management wants you to create a visual
Q240: You and your project team are just
Q241: Which of the following DoD directives is
Q242: Joan is a project management consultant and
Q243: You are the project manager for GHY
Q245: Which of the following is used to
Q246: Sam is the project manager of a
Q247: You work as a project manager for
Q248: Mark works as a Network Administrator for
Q249: DIACAP applies to the acquisition, operation, and
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents