Solved

Tom Is the Project Manager for His Organization

Question 244

Multiple Choice

Tom is the project manager for his organization. In his project he has recently finished the risk response planning. He tells his manager that he will now need to update the cost and schedule baselines. Why would the risk response planning cause Tom the need to update the cost and schedule baselines?


A) New or omitted work as part of a risk response can cause changes to the cost and/or schedule baseline.
B) Risk responses protect the time and investment of the project.
C) Baselines should not be updated, but refined through versions.
D) Risk responses may take time and money to implement.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents