Nancy is the project manager of the NHH project. She and the project team have identified a significant risk in the project during the qualitative risk analysis process. Bob is familiar with the technology that the risk is affecting and proposes to Nancy a solution to the risk event. Nancy tells Bob that she has noted his response, but the risk really needs to pass through the quantitative risk analysis process before creating responses. Bob disagrees and ensures Nancy that his response is most appropriate for the identified risk. Who is correct in this scenario?
A) Bob is correct. Bob is familiar with the technology and the risk event so his response should be implemented.
B) Nancy is correct. Because Nancy is the project manager she can determine the correct procedures for risk analysis and risk responses. In addition, she has noted the risk response that Bob recommends.
C) Nancy is correct. All risks of significant probability and impact should pass the quantitative risk analysis process before risk responses are created.
D) Bob is correct. Not all risk events have to pass the quantitative risk analysis process to develop effective risk responses.
Correct Answer:
Verified
Q288: Which of the following documents is used
Q289: You are responsible for network and information
Q290: Which of the following describes residual risk
Q291: Which of the following documents is described
Q292: What NIACAP certification levels are recommended by
Q294: Ned is the program manager for his
Q295: Which of the following terms related to
Q296: The Phase 4 of DITSCAP C&A is
Q297: Which of the following statements about the
Q298: You are the project manager of the
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents