Solved

You Work as a Project Manager for BlueWell Inc

Question 305

Multiple Choice

You work as a project manager for BlueWell Inc. There has been a delay in your project work that is adversely affecting the project schedule. You decided, with your stakeholders' approval, to fast track the project work to get the project done faster. When you fast track the project which of the following are likely to increase?


A) Quality control concerns
B) Costs
C) Risks
D) Human resource needs

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge