Traditional Work Breakdown Structures tend to
A) focus on the design of the system as oppose to the needs of the current phase and iteration
B) force too many levels of detail early on for large project and they tend to allow too few level of detail for small projects
C) be too specific for the project and difficult to compare across projects
D) all of the above
E) none of the above
Correct Answer:
Verified
Q21: Function points are used to measure the
Q22: To identify the tasks for a work
Q26: A critical success factor for project management
Q29: One method of estimating project time is
Q30: Ryan, a newly hired systems analyst /
Q30: The _ is a dynamic schedule that
Q32: When estimating project time schedules using industry
Q33: Adding people to a project team in
Q35: The most significant challenge to project managers
Q39: When using a function point estimation worksheet,
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents