Solved

A Suggested Project Requires Initial Fixed Assets of $227,000, Has

Question 80

Multiple Choice
A suggested project requires initial fixed assets of $227,000, has a life of 4 years, and has no salvage value. Assume depreciation is straight-line to zero over the life of the project. Sales are projected at 31,000 units per year, the price per unit is $47, variable cost per unit is $23, and fixed costs are $842,900 per year. The tax rate is 23 percent and the required return is 11.5 percent. Suppose the projections given for price and quantity can vary by ±4 percent while variable and fixed cost estimates are accurate to within ±2 percent. What is the best-case NPV?
A) $4,613
B) −$67,008
C) $127,511
D) $82,409
E) −$132,194

A suggested project requires initial fixed assets of $227,000, has a life of 4 years, and has no salvage value. Assume depreciation is straight-line to zero over the life of the project. Sales are projected at 31,000 units per year, the price per unit is $47, variable cost per unit is $23, and fixed costs are $842,900 per year. The tax rate is 23 percent and the required return is 11.5 percent. Suppose the projections given for price and quantity can vary by ±4 percent while variable and fixed cost estimates are accurate to within ±2 percent. What is the best-case NPV?


A) $4,613
B) −$67,008
C) $127,511
D) $82,409
E) −$132,194

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents