Given the below figure what tasks are included in the critical path?
A) 1, 2, 3, 4, 5, 6, 7
B) 1, 2, 3, 6, 7
C) 1, 2, 4, 6, 7
D) 1, 2, 5, 6, 7
Correct Answer:
Verified