Which is NOT a criterion that is used to determine how to define tasks for a work breakdown structure.
A) How to know when the task is complete.
B) How to estimate the effort required.
C) A logical way to determine its predecessor.
D) It should take one to five days.
Correct Answer:
Verified
Q12: The present value of $200,000 development costs
Q48: The person or group that work directly
Q49: A project management guide and standard of
Q50: Which would be the least desirable reason
Q51: Given a project schedule with all tasks
Q52: When the project team asks "Are our
Q54: Which of the following is NOT one
Q55: The benefits that accrue to an organization,usually
Q57: The _ consists of clients and key
Q58: A document to help define the scope