List in the correct sequence the first three tests to be carried out on a new 3 phase industrial cooker circuit
A) Continuity of cpc, insulation resistance an polarity
B) Polarity, continuity of cpc and insulation resistance
C) Visual inspection, earth fault loop and continuity of cpc
D) Polarity, earth fault loop impedance and insulation resistance
Correct Answer:
Verified
Q1: The documents which should be completed after
Q2: The statutory document which relates to the
Q3: Who should be consulted with regards to
Q4: When and where should the extent and
Q6: What would be the most appropriate way
Q7: The maximum length of 10mm2 cable which
Q8: When carrying out the 1st stage of
Q9: Stage one of a ring final circuit
Q10: The effect on the measured value of
Q11: The measured value of insulation resistance when
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents