Three Checks Which Must Be Carried Out on an Electrical

Question 9

Multiple Choice

Three checks which must be carried out on an electrical installation before an installation resistance test is carried out on it are


A) Installation isolated, lamps removed, switches open
B) Lamps removed, installation energised and dimmers bypassed
C) Installation energised, all lamps in place and switches closed
D) Switches closed, installation isolated and lamps removed

Correct Answer:

verifed

Verified