The first three tests required for an initial verification are
A) Polarity, Insulation resistance and earth fault loop
B) Continuity of protective conductors, polarity and insulation resistance
C) Ring final circuit test, insulation resistance and earth fault loop impedance
D) Continuity of protective conductors, ring final circuit test and insulation resistance
Correct Answer:
Verified
Q8: The calculation for circuit earth fault loop
Q9: A conductor which is 36 m long
Q10: The circuits in an installation have an
Q11: The test which must be carried out
Q12: The tests currents required when testing a
Q14: The maximum rating of an RCD used
Q15: The correct IP rating for equipment installed
Q16: The IP rating used to indicate finger
Q17: The current which should cause automatic disconnection
Q18: The stated maximum Ze for a TN-S
Unlock this Answer For Free Now!