A monolithic screed differs from a separate screed in that it
A) Must be placed within 3 hours of the base being laid
B) Must be placed after the base has hardened
C) Must be placed on a dampened concrete surface
D) Must be placed on a surface treated with a bonding agent
E) Must be placed to a minimum thickness of 37mm
Correct Answer:
Verified
Q1: A functional requirement of an internal finish
Q2: One advantage of applying a screed to
Q4: One disadvantage of unbonded screeds is
A) They
Q5: Floating screeds are mainly used to
A) Improve
Q6: Terrazzo is a floor finish that is
Q7: The sustainability credentials of synthetic rubber sheet
Q8: One advantage of dry lining is
A) It
Q9: The spacing of the metal furrings used
Q10: Coving is used on ceiling finishes to
A)