Fact Pattern 13-4
Teatro Restoration, Inc., begins renovating an old theater for Urban Edge Productions, but after three months Teatro demands an extra $250,000. Urban Edge agrees to pay.
-Refer to Fact Pattern 13-4. If Teatro says it is asking for the extra $250,000 because it has encountered extraordinary unforeseen difficulties that will add considerable cost to the project, the agreement is
A) enforceable as the consideration is past.
B) enforceable because of unforeseen difficulties.
C) unenforceable as an illusory promise.
D) unenforceable due to the preexisting duty rule.
Correct Answer:
Verified
Q44: Rory questions whether there is consideration for
Q45: Digital Enterprise, Inc., promises to pay its
Q47: Fact Pattern 13-3
Sal contracts with Tasty Pizza
Q48: Frisco offers to buy a Gibson guitar
Q49: Delightful Weddings, LLC, and Event Catering Inc.
Q51: Maria is the sheriff of Narez, Texas.
Q52: D'Sean promises to pay his personal assistant
Q54: Kent buys Lizzie's house for $100,000, which
Q54: Industrial Engineering, Inc., promises to give stock
Q55: Fact Pattern 13-2
Boyd defends against a breach-of-contract
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents