In Construction Contracts, Penalty Clauses Are Technically Called "Liquidated Damages

Question 21

True/False

In construction contracts, penalty clauses are technically called "liquidated damages clauses;" if they are labeled "penalty" clauses, there is a long line of cases that say they are not enforceable.

Correct Answer: