If a Supplier might go bankrupt, the Contract Administrator should
A) get a copy of keys to any storage of materials the Contractor might need
B) have material delivered to the project site or other facility
C) wait for notification of the bankruptcy so no one is pushed into the situation
D) cancel the order and get a new supplier
Correct Answer:
Verified
Q1: Acceleration clauses cannot require a Constructor to
Q2: Generally not included in a Time and
Q3: For progress billing, the Contract Administrator should
Q5: If there is a ""no damage for
Q6: If a hazardous substance is exposed
A) the
Q7: When terminating for cause
A) be sure all
Q8: Exculpatory clauses
A) usually contain risks that are
Q9: Indemnity clauses
A) usually contain issues that are
Q10: Contractors should be alert to hazardous substances
Q11: It is often said that the most
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents