Liquidated damages result from
A) water damage usually during the foundation stage
B) water damage during any part of the construction
C) failing to meet the completion date
D) the owner becoming bankrupt and going out of business
Correct Answer:
Verified
Q11: Two clauses that help interpret the contract
Q12: The first level of interpreting a Contract
Q13: When submitting an RFI, the Contractor should
Q14: Although many may have a say, a
Q15: Cardinal changes
A) can be based on scope
Q17: Means and methods will
A) always be provided
Q18: The Spearin Doctrine
A) relieves the Contractor from
Q19: The Spearin Doctrine relieves Design Professionals from
Q20: A Subcontractor cannot be held responsible for
Q21: Generally specific will govern over general in