With a Differing Site Condition, the Contract Administrator should
A) fully document all aspects of the different condition
B) meet as quickly as possible to brainstorm solutions
C) notify all parties immediately
D) all of these
Correct Answer:
Verified
Q1: Acting conscionably means to act prudently in
Q2: In order to avoid responsibility, the Owner
Q4: With a Differing Site Condition
A) the Contract
Q5: Type II Differing Site Conditions
A) differ from
Q6: Type I Differing Site Conditions
A) differ from
Q7: Reliance upon the Spearin Doctrine is sufficient
Q8: Type I Differing Site Conditions should have
Q9: Differing Site Conditions usually refers to something
Q10: A Type II Differing Site Condition is
Q11: A Type I Differing Site Condition is