Related to warranty periods
A) The Contract Administrator should make sure manufacturer's agreed warranties coincide with the project requirements
B) The Contract Administrator should pass on only those warranties that are still in place
C) Never pay more for what is required in the Contract warranty period
D) The Contract Administrator should begin all warranties at the time of Substantial completion
Correct Answer:
Verified
Q1: A Contractor should check the Contract to
Q3: Expressed authority is
A) Usually detailed at the
Q4: The Owner reserves the right in regard
Q5: When it comes to quality
A) The Architect
Q6: The process of project closeout
A) Begins upon
Q7: Final payment guarantees the Constructor that everything
Q8: Apparent authority of the Design Professional comes
Q9: Commissioning a building is a new process
Q10: Approving payment requests gives the Design Professional
Q11: Staying past final acceptance to maintain the
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents