When developing test scope, which recommendation should be followed?
A) Test the entire BCP immediately to determine outages and then focus on those outages with subsequent tests
B) Pick the most likely aspects of the BCP to fail and test those first
C) Begin the testing with small, simple tests and then based on the results of those tests, increase scope accordingly
D) Testing should be randomized to provide accurate results
Correct Answer:
Verified
Q14: Mr) Newbie has recently joined the Crisis
Q15: What documentation is recommended for use when
Q16: External resources such as Fire and Public
Q17: Why should testing be a key component
Q18: What should be the first step in
Q20: When monitoring the testing of the Business
Q21: BCP testing scenarios should be designed using
Q22: A risk trigger is what triggers a
Q23: Which of these test exercises should be
Q24: Which of these testing types is a
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents