Given the following activities, their durations, and the predecessor relationships, construct the network flow diagram and answer the questions that follow.
\begin{tabular}{|c|c|c|c|c|}
\hline & & & & \\
\hline & - & 7 & 10 & 13 \\
\hline & & 5 & 11 & 23 \\
\hline & & 11 & 15 & 19 \\
\hline & & 4 & 5 & 6 \\
\hline & & 9 & 11 & 25 \\
\hline & & 5 & 6 & 7 \\
\hline & & 5 & 5 & 5 \\
\hline & & 9 & 11 & 13 \\
\hline & & 7 & 11 & 15 \\
\hline & & 4 & 5 & 6 \\
\hline
\end{tabular}
A) What is the expected time for activity E?
B) What is the variance for activity E?
C) What is the critical path based on the calculation of the estimated times?
D) What is the estimated duration of the critical path?
E) What is the estimated variance along the critical path?
F) What is the probability of completion of the project before hour 45?
Correct Answer:
Answered by Quizplus AI
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q82: Any activity that cannot be delayed without
Q83: _ a project involves reducing expected project
Q84: Projects fail because of deficient _ or
Q85: _ from finance is finding use in
Q86: What are the three main goals of
Q87: How would you describe the responsibilities of
Q88: What characteristics should you consider when selecting
Q89: Describe and explain the five planning steps
Q90: Draw the project network based on
Q92: Use the data from problem 21
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents