A sunk cost is:
A) The cost of foundations sunk in the ground.
B) A cost that always varies in line with sales and management cannot change this relationship.
C) A cost relating to an event that has already occurred and cannot be altered.
D) A cost that is recurring.
E) None of the above
Correct Answer: